Provincial Highway 9 traffic control information for July 2019
1.The 137 km + 500 m (Wuta section) of Provincial Highway 9 will be under construction for improvement of the slope stabilization.
The construction begins at 8:00 am –17:00 pm
Control schedule: June 25 - July 12 2019
Passage Time: Every 30 minutes.
2. The 144 km + 700 m ~ 146 km of Provincial Highway 9 will be under construction for improvement of the highway drainage.
The construction begins at 8:00 am –17:00 pm
Control schedule: June 25 - July 31 2019
Passage Time: Not predetermined - accessibility depends on construction conditions.
3. The 158 km (Hepin Township) of Provincial Highway 9 will be under construction for the highway channelization island construction.
Control schedule: June 4 - July 18 2019
Passage Time: Accessibility follows the traffic lights. Open one direction of traffic once at a time for both direction traffic. Road users are advised to follow the construction on-site personnel’s direction.
Note: Traffic control for all the above construction sites do not apply on weekends and public holidays.
Notice from Directorate General of Highways: Please pay attention for own safety. In the event of an earthquake or a week after heavy rains, please do not enter the mountain road. Plan ahead before your trip. Have a safe and pleasant journey!
Road Repair Unit: Directorate General of Highways, Nan’ao Maintenance Office, Section Chief Mr. Zhuan, Shi-Zhen TEL: 03-9982161 & Hualien Maintenance Office TEL: 03-8230570
News issued by Directorate General of Highways, MOTC, The fourth Maintenance Construction office & Hualien Maintenance Office